The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

Once such a river segment has been found to be ineligible, the agency will manage the river and its corridor based on the underlying management direction in its programmatic plan and need no longer protect it as a potential wild and scenic river.

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.

Yes. Section 7(b) of the Wild & Scenic Rivers Act provides the same protection to study rivers authorized by Congress, except that the qualifying word “unreasonably” does not appear before “diminish” for projects located above, below, or on a stream tributary to the study segment’s boundaries. The intent and effect is to provide greater protection for study rivers from proposed hydroelectric facilities or other federally assisted water resource projects during the time-limited study process. Identical protection from water resource projects also applies to rivers that were previously...

The river-administering agency is obligated to identify, monitor and report violations of water quality standards to the appropriate federal or state agency. In addition, the river-administering agency often develops and implements management actions to protect and enhance water quality through partnerships with local and state agencies, and water conservation districts. The Wild & Scenic Rivers Act, however, does not reassign EPA and/or state responsibility for implementation of the Clean Water Act to the river-administering agency.

Section 10(a) of the Wild and Scenic Rivers Wild & Scenic Rivers Act directs that:

Each component of the national wild and scenic rivers system shall be administered in such manner as to protect and enhance the values which caused it to be included in said system without, insofar as is consistent therewith, limiting other uses that do not substantially interfere with public use and enjoyment of these values.

In its technical report on managing wild and scenic rivers (Wild and Scenic River Management Responsibilities (2002)) the...

(*For certain rivers, Congress directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground practicalities and, therefore, are unlikely to require subsequent amendment.)

Yes. While Congress specifies the segment divisions of a designated river, in some instances congressional language may require interpretation. For example, a segment division between a wild and scenic classification described as “from the bridge”...

Camping is often important to the enjoyment of wild and scenic rivers. As appropriate, and when private interests do not provide sufficient facilities, the federal managing agency attempts to provide them on federal lands. As a condition of use, consistent with river classification and the management objectives for the river area, the managing agency may specify that camping will be permitted only in designated locations. Enforcement of camping restrictions and limitations can be through indirect means (brochures, maps, signs, etc.) and/or direct means (permits, enforcement personnel, etc...

Most rivers have flexible boundaries to accommodate specific features and river values. (Refer to Establishment of Wild and Scenic River Boundaries (1998).)

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

WSR designation seeks to protect and enhance a river’s current natural condition and provide for public use consistent with retaining those values. Designation affords certain legal protection from adverse development, e.g., no new dams may be constructed, nor federally assisted water resource development projects allowed that are judged to have an adverse effect on designated river values. Where private lands are involved, the federal managing agency will work with local governments and owners to develop voluntary protective measures.

Landowners can charge a fee for crossing private lands to fish, except where a public access easement exists. The designation of a wild and scenic river does not change landowner rights unless all, or a portion of those use rights, are acquired from the landowner.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

Wild and scenic river study reports are prepared in three instances:

  1. When Congress authorizes a study pursuant to Section 5(a) of the Wild & Scenic Rivers Act.

  2. For eligible rivers that have also been determined suitable by a federal land management agency pursuant to Section 5(d)(1) of the Wild & Scenic Rivers Act, when the agency deems it appropriate to forward the recommendation.

  3. For state-nominated Section 2(a)(ii) rivers, the National Park Service prepares a report determining whether the candidate river meets the requirements of...

Easements on private lands acquired for the purposes of protecting wild and scenic rivers do not provide public access unless this right was specifically acquired from the private landowner. A trail or road easement by necessity would involve public use provisions. Any provisions for public use of private lands must be specifically purchased from the landowner.

Yes. Section 6(b) of the Wild & Scenic Rivers Act specifically prohibits the use of condemnation for fee title purchase of private lands if 50 percent or more of the acreage within the boundaries on both sides of the designated river is in public ownership (i.e., owned by the federal, state, or local government). In addition, Section 6(a)(1) of the Wild & Scenic Rivers Act prohibits acquiring more than 100 acres per river mile within the corridor, which equates to a stip of land about 400-feet wide along both sides of the river. Fee title condemnation is allowed to clear title or...

Yes. The Wild & Scenic Rivers Act anticipates the need for occasional adjustment of the lateral (river corridor) boundary, directing that such amendment follow the same process as described for the initial boundary development in Sections 3(b) and (c) of the Wild & Scenic Rivers Act. The legally established river corridor might require amendment to better reflect protection of outstandingly remarkable values or as the result of identification of a new outstandingly remarkable value.

For state-designated rivers, a governor may submit an application to the Secretary of the Interior under Section 2(a)(ii) of the Act.  If found eligible, and if sufficient protection is afforded by the state, the Secretary may make the designation.  Rivers designated in this manner continue to be administered by the state (sometimes with assistance from local governments), except for any federal lands along the river.  If there are federal lands located along the river, the state and federal river-administering agencies may enter into an agreement to outline federal/state...

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

Section 16(c) of the Wild & Scenic Rivers Act defines a scenic easement as follows:

“Scenic easement” means the right to control the use of land (including the air space above such land) within the authorized boundaries of a component of the wild and scenic river system, for the purpose of protecting the natural qualities of a designated wild, scenic, or recreational river area, but such control shall not affect, without the owner’s consent, any regular use exercised prior to the acquisition of the easement.

While the Wild & Scenic Rivers...

Yes, but with many restrictions. It is important to note that condemnation is a tool that has been used only rarely on wild and scenic rivers. The objective of wild and scenic river designation is to protect and, as possible, enhance the values which caused the river to be designated. Should some proposed or actual use clearly threaten the values the river was designated to protect, the river managing agency would work with a landowner to explore ways to avert the threat through local zoning, state provisions, land exchanges, or purchases on a willing-seller/willing-buyer basis....

There are more appropriate and cost-effective ways to ensure resource conservation along wild and scenic rivers than using the Wild & Scenic Rivers Act’s condemnation authority. (Refer to Protecting Resource Values on Non-federal Lands (1996).)

Agencies may acquire properties using appropriated funds under the Land and Water Conservation Fund Act or other authorities. Owners are contacted in order to see if an exchange or voluntary purchase can be negotiated.

Section 8(a) of the Wild & Scenic Rivers Act withdraws public (federal) lands within the authorized boundary of a designated component from entry, sale, or other disposition under the public land laws of the United States.

Land acquisition is one tool for protecting and enhancing river values. It may also be an important means of providing public access to a wild and scenic river. Notwithstanding Section 6 of the Wild & Scenic Rivers Act, however, Congress has pre-empted some or all of the Wild & Scenic Rivers Act’s federal land acquisition authorities in the enabling acts for certain wild and scenic rivers where the river study demonstrated that protective zoning or other conservation practices provided adequate safeguards for river values.

River-administering agencies use a variety of approaches to protect or enhance water quality including, but not limited to: developing a cooperative water quality plan with the EPA and state agencies; securing cooperative funding to assess or remediate problems; and providing technical assistance to landowners and communities, often through local conservation districts.

Yes. To withdraw a scenic or recreational river segment, the managing agency must submit a separate public land order or notice of realty action.

No. The United States determines the quantity necessary to protect flow-dependent outstandingly remarkable values.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

The economic impacts of implementing various alternatives should be addressed through the evaluation process to determine whether a river is a suitable addition to the National Wild & Scenic Rivers System or through the river management planning process, or a designated wild and scenic river. Economic issues, such as development and ecotourism, both inside and outside of potentially designated river corridors may be considered.

Circumstances where agencies should always seek information and advice from each other are:

  1. In agency inventory and planning processes, and environmental analysis processes for aquatic ecosystems and regional watersheds; and,
  2. When proposed actions have the potential of affecting other agency-administered portions of the river.

Yes, the federal government may seek to control use on adjacent lands under very limited circumstances. The Constitution gives the federal government certain limited powers to control uses on state-owned lands that affect adjacent federal property. These powers may be exercised through the Property Clause, which provides that, “Congress shall have the power to make all needful rules and regulations respecting the territory or the property belonging to the United States.”

The federal government may also regulate use and/or activities occurring on the surface waters...

Once such a river segment has been found to be ineligible, the agency will describe the basis for this finding in the study report and follow its internal procedures to transmit the report to the Congress in accordance with Section 7(b) of the Wild & Scenic Rivers Act.

Prior to 1986, Section 3(b) of the Wild & Scenic Rivers Act required the river-administering agency to “prepare a plan for necessary developments in connection with its administration in accordance with such classification.” Through a generic amendment of the Wild & Scenic Rivers Act in 1986, Section 3 was amended with a new subsection requiring a “comprehensive management plan . . . to provide for protection of the river values” (Section 3(d)(1)). The comprehensive river management plan (CRMP) must address:

  1. Resource protection;

  2. Development of lands...

Section 6(c) of the Wild & Scenic Rivers Act states:

. . . the appropriate Secretary shall issue guidelines, specifying standards for local zoning ordinances, which are consistent with the purposes of this Act. The standards specified in such guidelines shall have the object of (a) prohibiting new commercial or industrial uses other than commercial or industrial uses which are consistent with the purposes of this Act, and (b) the protection of the bank lands by means of acreage, frontage, and setback requirements on development.

The Wild...

Under Section 5(a), Congress directs that a study be conducted on identified river segments (usually within three years).  The designated federal agency conducts a study and subsequently reports its findings through the appropriate Secretary.  As a general rule, where joint agency jurisdictions are involved, the cooperating agencies coordinate their efforts prior to making recommendations or submitting reports.

Under Section 5(d)(1), federal agencies are directed to identify and evaluate potential additions to the National Wild & Scenic Rivers System through agency...

Eligibility findings are made as a part of a congressionally authorized study under Section 5(a), or pursuant to agency inventory and planning under Section 5(d)(1).  For Section 2(a)(ii) rivers, the National Park Service will make an eligibility determination under authority delegated by the Secretary of the Interior following application by the governor(s) for federal designation.

Due to the dams, diversions, and water resource development projects that occurred from the 1930’s to the 1960’s, the need for a national system of river protection was recognized by conservationists (notably Frank and John Craighead), congressional representatives (such as Frank Church and John Saylor), and federal agencies.  The Act was an outgrowth of the national conservation agenda of the 1950’s and 1960’s, captured in the 1962 recommendations of the Outdoor Recreation Resources Review Commission.  The Act concluded that selected rivers be preserved in a free-flowing...

No restrictions to private lands may be applied under the Wild & Scenic Rivers Act. Comprehensive river management plans may establish goals for new construction consistent with classification. There is a wide range of uses compatible with these classifications so long as the overall values and character of the river corridor is maintained. Any effect on private lands would be through state or local zoning. Federal acquisition of lands or development rights would require landowner compensation.

Yes.  The Nationwide Rivers Inventory lists potentially eligible rivers.  Federal agencies should make an eligibility determination for rivers on the Nationwide Rivers Inventory.

There are no known studies comparing river use levels before and after wild and scenic river designation with changes in use levels of similar non-wild and scenic rivers. Factors other than wild and scenic river designation (i.e., river and water attributes, access to the river, and availability of facilities and commercial services) are considered to be the major influences on river use levels. For wild and scenic rivers, as for other rivers managed by federal agencies, the implementation of permit systems or other limits of use are typically undertaken when use exceeds an acceptable...

No. Under the Wild & Scenic Rivers Act, the federal government has no authority to regulate or zone private lands. Land use controls on private lands are solely a matter of state and local zoning. Although the Wild & Scenic Rivers Act includes provisions encouraging the protection of river values through state and local governmental land use planning, there are no binding provisions on local governments. In the absence of state or local river protection provisions, the federal government may seek to protect values by providing technical assistance, entering into agreements with...

The government typically provides technical assistance to find ways to alleviate or mitigate the actual or potential threat(s). Purchasing a partial right (easement) or the property in fee title is usually the last resort. If an easement is purchased, the owner would sell certain development rights and receive a payment, yet retain title to the land.

Yes.  Congress and the Secretary of the Interior have designated many river segments which are above or below dams that have regulated flows.

No. The public’s right to float a particular river does not change with designation. Neither does designation give river users the right to use, occupy, or cross private property without permission.

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

A primary objective of wild and scenic river designation is to protect and enhance riparian area function and other river-related natural values. Specific actions to meet the objective are typically set forth in the management plan required for each river.

Should the purchase of land become necessary, condemnation is typically a last resort and only used when:

  1. Land is clearly needed to protect resource values, or provide necessary access for public recreational use, and a purchase price cannot be agreed upon.

  2. Clear title to a property is needed, in which case condemnation is merely a legal procedure that has nothing to do with government/landowner differences.