For rivers designated under Section 3(a) of the Wild & Scenic Rivers Act, a state’s responsibilities include:

  • Regulating and enforcing fishing and hunting regulations.

  • Adjudicating water rights and appropriation.

  • Developing and administering water quality standards.

  • Administering state land use regulations on non-federal lands.
  • Managing state lands and facilities along the river (e.g., state highways, parks, forests).

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.

Once rivers have been evaluated and determined eligible for further study, agencies conduct an evaluation to determine if the rivers are “suitable” or “not suitable” for wild and scenic river designation within their resource or land management planning processes (Section 5(d)(1)), or usually as a separate study for congressionally authorized studies (Section 5(a)). In each process, the benefits of protecting river values are weighed against other resource values, issues and alternatives.

Either process is typically accompanied by an environmental document, normally an...

A Section 5(d)(1) study river is protected to the extent of each study agency’s authority and not by the Wild & Scenic Rivers Act. Each agency’s policy is to protect eligible rivers and rivers determined suitable for designation for the life of the respective agency land use plan. A river determined not suitable for designation need no longer be protected as a potential addition to the National Wild & Scenic Rivers System once the study, with its related decision document, is completed.

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under the Wild & Scenic Rivers Act and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.

Yes. Such projects may be constructed to protect and enhance fish and wildlife. In-channel structures (e.g., placement of large wood to replicate natural stream conditions) and in-channel activities (e.g., dredging to protect listed species) are acceptable, provided they do not have a direct and adverse effect on the values of the river (its free-flowing condition, water quality, and outstandingly remarkable values. Similarly, in-channel habitat projects may also be constructed below/above a designated river so long as they do not unreasonably diminish the scenic, recreational, and fish...

The need to clarify a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the segment division to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the bridge”...

Section 6(a)(1) of the Wild & Scenic Rivers Act states:

The Secretary of the Interior and the Secretary of Agriculture are each authorized to acquire lands and interests in land within the authorized boundaries of any component of the national wild and scenic rivers system designated in Section 3 of this act . . . but he shall not acquire fee title to an average of more than 100 acres per mile on both sides of the rivers.

The Wild & Scenic Rivers Act authorizes fee title acquisition to the equivalent of about a 400 foot wide strip of land...

As provided in Sections 4(a) and 5(c) of the Wild & Scenic Rivers Act, the following factors should be considered and, as appropriate, documented as a basis for the suitability determination for each river.

  1. Characteristics which do or do not make the area a worthy addition to the National Wild & Scenic Rivers System. These characteristics are described in the Wild & Scenic Rivers Act (see factors 2 through 7) and may include additional suitability factors (8 through 13).

  2. The current status of land ownership and use in the area.

  3. The...

Yes. Motorized access allowed prior to designation will, generally, be allowed post designation, subject to congressional intent and river management objectives. However, if motorized use adversely impacts a river’s water quality or outstandingly remarkable values, or if the use is not consistent with the river’s classification the route may be closed or regulated.

The continued legality of motorized use on land or water is best determined through the river management planning process, which considers factors such as impacts on river values, user demand for such motorized...

Yes. In some river study authorizations Congress has required the study agency to work with state and local governments and the public to develop a CRMP in concert with the study process to assist in determination of the river’s suitability. Such pre-designation CRMPs have, in some cases, been adopted in the legislation adding the river to the National Wild & Scenic Rivers System. In cases where Congress has not authorized a pre-designation CRMP, agencies have taken the initiative to develop elements of the CRMP in the study report (pre-designation).

Once such a river segment has been found to be ineligible, the agency will manage the river and its corridor based on the underlying management direction in its programmatic plan and need no longer protect it as a potential wild and scenic river.

The following summarizes the sections of the Wild & Scenic Rivers Act related to water resources (quality and quantity):

Section 1(b) of the Wild & Scenic Rivers Act establishes that the national policy of dam and other construction be complemented by a policy that would preserve other selected rivers or sections thereof “in their free-flowing condition to protect the water quality of such rivers and to fulfill other vital national conservation purposes.”

Section 10(a) states: “Each component of the national wild and scenic rivers system shall be administered in...

No. Under the Wild & Scenic Rivers Act, the federal government has no authority to regulate or zone private lands. Land use controls on private lands are solely a matter of state and local zoning. Although the Wild & Scenic Rivers Act includes provisions encouraging the protection of river values through state and local governmental land use planning, there are no binding provisions on local governments. In the absence of state or local river protection provisions, the federal government may seek to protect values by providing technical assistance, entering into agreements with...

The Interagency Guidelines interpret Section 10(a) of Wild & Scenic Rivers Act (the protect and enhance mandate) as “a non-degradation and enhancement policy for all designated river areas, regardless of classification. . . . Specific management strategies will vary according to classification but will always be designed to protect and enhance the values of the river area.” The overarching goal articulated in Section 10(a) is to protect existing high-quality conditions while improving conditions when unacceptable impacts are documented, thus leaving each river to future generations in...

No. The Wild & Scenic Rivers Act specifically prohibits the federal government from expending funds on Section 2(a)(ii) rivers, except to manage federal lands or to provide technical assistance to local managers.

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

Suitability is an assessment of factors to provide the basis for determining whether to recommend a river for addition to the National Wild & Scenic Rivers System. Suitability is designed to answer these questions:

  1. Should the river’s free-flowing character, water quality, and outstandingly remarkable values (ORVs) be protected, or are one or more other uses important enough to warrant doing otherwise?

  2. Will the river’s free-flowing character, water quality, and ORVs be protected through designation? Is it the best method for protecting the river corridor...

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

The priority date is the date the river was added to the National Wild & Scenic Rivers System.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

The Wild & Scenic Rivers Act does not specifically mention aquatic or upland non-indigenous species. While non-indigenous species may be introduced—provided that doing so is not contrary to another law or the policy of the managing agency, and would not result in the degradation to the river’s values—the use of native species is generally preferred. Indirect impacts of introducing non-indigenous species, e.g., increasing recreational fishing, should also be considered. Additional guidance for a specific river is usually included in its management plan.

Yes. To withdraw a scenic or recreational river segment, the managing agency must submit a separate public land order or notice of realty action.

The Act (Public Law 90-542; 16 U.S.C. 1271-1287) was signed on October 2, 1968. It has been amended many times, primarily to designate additional rivers and authorize additional rivers for study for possible inclusion.

Yes, per Sections 3(b) and 15(1) for rivers designated by Congress under Section 3(a), but not for rivers designated by the Secretary of the Interior under Section 2(a)(ii). For 2(a)(ii) rivers, states and/or local government set the boundaries, if any, for rivers in their systems; these rivers are not subject to Section 3(b) or the 320/640-acre limitation.

Generally, existing livestock grazing practices and related structures are not affected by designation. The Interagency Guidelines state that agricultural practices should be similar in nature and intensity to those present in the area at the time of designation, and that grazing may be compatible with all river classifications (wild, scenic or recreational). Grazing and other public uses may occur in a wild and scenic river corridor as long as the uses do not adversely impact or otherwise degrade the values for which a river was designated.

No. Non-indigenous species need not be removed unless they are degrading other important resource values. Practical considerations, such as the effort or expense of eradicating a non-indigenous species and its importance (e.g., game species), should also be considered. This issue is generally addressed in the management plan.

Circumstances where agencies should always seek information and advice from each other are:

  1. In agency inventory and planning processes, and environmental analysis processes for aquatic ecosystems and regional watersheds; and,
  2. When proposed actions have the potential of affecting other agency-administered portions of the river.

River segments may be tentatively classified for protective management purposes prior to a final suitability determination and/or congressional action.  This ensures that river values and characteristics are protected (subject to agency policies and standards) until the evaluation process and possible designation is completed.

The study report for a congressionally authorized Section 5(a) study river is required to be forwarded by the study agency within the period specified in Section 5(b). This study report must be forwarded to Congress no matter what the outcome of the study.

Unlike the firm deadlines established for Section 5(a) study reports, the Act is silent in regard to Section 5(d)(1) rivers. Thus the river-administering agencies have considerable latitude in how and when to transmit the study report for rivers they have found suitable and are recommending to Congress for designation. The...

Once such a river segment has been found to be ineligible, the agency will describe the basis for this finding in the study report and follow its internal procedures to transmit the report to the Congress in accordance with Section 7(b) of the Wild & Scenic Rivers Act.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

(*For certain rivers, Congress directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground practicalities and, therefore, are unlikely to require subsequent amendment.)

Yes. While Congress specifies the segment divisions of a designated river, in some instances congressional language may require interpretation. For example, a segment division between a wild and scenic classification described as “from the bridge”...

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

It is important to develop and apply standardized criteria through a documented evaluation process that may include a screening for potential wild and scenic rivers. If there doubt, evaluate the river according to the criteria in the Wild & Scenic Rivers Act, i.e., free-flowing condition and outstandingly remarkable values.

The economic impacts of implementing various alternatives should be addressed through the evaluation process to determine whether a river is a suitable addition to the National Wild & Scenic Rivers System or through the river management planning process, or a designated wild and scenic river. Economic issues, such as development and ecotourism, both inside and outside of potentially designated river corridors may be considered.

Yes. Section 7(b) of the Wild & Scenic Rivers Act provides the same protection to study rivers authorized by Congress, except that the qualifying word “unreasonably” does not appear before “diminish” for projects located above, below, or on a stream tributary to the study segment’s boundaries. The intent and effect is to provide greater protection for study rivers from proposed hydroelectric facilities or other federally assisted water resource projects during the time-limited study process. Identical protection from water resource projects also applies to rivers that were previously...

To be eligible for designation, a river must be free-flowing and contain at least one "outstandingly remarkable value," i.e., scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar value.

Many individuals and communities support designation to help focus management efforts on protecting and enhancing river values. The intent of the Wild & Scenic Rivers Act is to build partnerships among landowners, river users, tribal nations and all levels of governments in developing goals for river protection. Designation provides strong protection against construction of new dams and projects that alter the free-flowing condition, water quality, and outstandingly remarkable values for which the river was designated.

It depends on whether the collecting activity is commercial or noncommercial in nature and subject to river-administering agency regulation. Mining under the 1872 mining law is a commercial and business activity tied to valid existing rights of claims and is regulated as such (36 CFR 228, 43 CFR 3809, 8365, et al).

Non-commercial mineral collecting for recreational purposes (e.g., hobby collecting, rock-hounding, gold panning, sluicing, or dredging) may be authorized by the Bureau of Land Management or the U.S. Forest Service depending on the amounts collected, size and scale of...

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

Yes it may. Once water rights are adjudicated, the federal reserved water right may affect future water development projects, depending upon the impacts of the new proposal on the river’s flow-dependent values. Adjudications have been completed or are in process on 15 designated wild and scenic rivers. To date, existing flows have been sufficient to protect current and future demands and to meet the purposes for which the river was designated. River-administering agencies can work with local and state agencies to negotiate solutions that accommodate future water needs and that protect wild...

Yes. Section 6(b) of the Wild & Scenic Rivers Act specifically prohibits the use of condemnation for fee title purchase of private lands if 50 percent or more of the acreage within the boundaries on both sides of the designated river is in public ownership (i.e., owned by the federal, state, or local government). In addition, Section 6(a)(1) of the Wild & Scenic Rivers Act prohibits acquiring more than 100 acres per river mile within the corridor, which equates to a stip of land about 400-feet wide along both sides of the river. Fee title condemnation is allowed to clear title or...

Once determined eligible, river segments are tentatively classified for study as either wild, scenic, or recreational based on the level of development of the shoreline, watercourse and access at the time of river is found eligible. If designated by Congress, the river’s enabling legislation generally specifies the classification.

No restrictions to private lands may be applied under the Wild & Scenic Rivers Act. Comprehensive river management plans may establish goals for new construction consistent with classification. There is a wide range of uses compatible with these classifications so long as the overall values and character of the river corridor is maintained. Any effect on private lands would be through state or local zoning. Federal acquisition of lands or development rights would require landowner compensation.

The Wild & Scenic Rivers Act requires that detailed boundaries portrayed on maps be established and submitted to Congress within one year of designation. Agencies may finalize boundaries through their respective land management planning process.

Pending the establishment of detailed river boundaries, the Wild & Scenic Rivers Act specifies that the interim boundary is one-quarter mile on each side of the river as measured from the ordinary high water mark.

Section 3(b) of the Wild & Scenic Rivers Act states:

The agency charged with the...

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

There are two ways rivers are designated in the National Wild & Scenic Rivers System:

  • By Act of Congress
    This requires legislation to amend Section 3(a) of the Act.  Rivers designated by Congress are listed in Section 3(a) of the Act.
  • By the Secretary of the Interior
    This...

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under various laws and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.