The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

Section 8(a) of the Wild & Scenic Rivers Act withdraws public (federal) lands within the authorized boundary of a designated component from entry, sale, or other disposition under the public land laws of the United States.

Administering agencies do not have any authority to control public use of private lands. Granting of access remains the owner’s responsibility and trespass is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

There are two ways rivers are designated in the National Wild & Scenic Rivers System:

  • By Act of Congress
    This requires legislation to amend Section 3(a) of the Act.  Rivers designated by Congress are listed in Section 3(a) of the Act.
  • By the Secretary of the Interior
    This requires...

Some examples of other similar outstandingly remarkable values include botanical, hydrological, paleontological, scientific, or heritage values.

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

Yes, if they are consistent with management objectives for the river and do not degrade water quality or the outstandingly remarkable values for which the river was designated.

No. The public’s right to float a particular river does not change with designation. Neither does designation give river users the right to use, occupy, or cross private property without permission.

Timber management activities on federal lands within wild and scenic river corridors must be designed to help achieve land-management objectives consistent with the protection and enhancement of the values that caused the river to be added to the National Wild & Scenic Rivers System. Management direction needed to protect and enhance the river’s values is developed through the river planning process. Wild and scenic river designation is not likely to significantly affect timber management activities beyond existing measures to protect riparian zones, wetlands, and other resource values...

The Department of Transportation (DOT), in coordination with the river-administering agency, performs compliance reviews for qualifying properties. While Section 4(f) requires that the river-administering agency’s recommendations for minimizing harm are considered during the planning process, the authority to administer and make Section 4(f) approvals ultimately resides with the DOT. The river-administering agency’s concurrence on any DOT Section 4(f) compliance documents should clearly state that its concurrence is contingent upon a favorable final determination for the project under...

The Wild & Scenic Rivers Act states that rivers designated under Section 2(a)(ii) “shall be administered by the State or political subdivision thereof without expense to the United States other than for administration and management of federally owned lands.” The state is responsible for providing protection, except on federally administered lands and with respect to Section 7(a) determinations and securing a federal reserved water right under Section 13(c), both of which are made by a federal agency. The National Park Service provides ongoing technical assistance and partnership...

Differences include, but are not limited to, the following areas:

  1. Motorized boats and other motors may be allowed in wild and scenic rivers classified as wild, whereas the administering Secretary has the discretion to continue the use of motorized boats and airplane landings in wilderness where such uses are traditionally established. In areas that are both a wild and scenic river and wilderness, the most restrictive provisions of the two acts apply, subject to any area-specific legislative language.

  2. New dams are prohibited in wild and scenic rivers. The...

Once determined eligible, river segments are tentatively classified for study as either wild, scenic, or recreational based on the level of development of the shoreline, watercourse and access at the time of river is found eligible. If designated by Congress, the river’s enabling legislation generally specifies the classification.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

The economic impacts of implementing various alternatives should be addressed through the evaluation process to determine whether a river is a suitable addition to the National Wild & Scenic Rivers System or through the river management planning process, or a designated wild and scenic river. Economic issues, such as development and ecotourism, both inside and outside of potentially designated river corridors may be considered.

Wild and scenic river status does not provide federal authority to regulate private lands. The river-administering agency will cooperate with state and local agencies to appropriately monitor and evaluate activities on private land. If such activities (existing or potential) threaten or are incompatible with the values that contributed to the river’s designation, then, to the extent necessary, mitigation will be accomplished in cooperation with landowners and federal, state and local agencies.

Wild and scenic river designations generally cause property values to remain stable or increase. For example, see Economic Benefits of Conserved Rivers: An Annotated Bibliography (Porter, B., Collier, S., Becerra, N., and Schultz, J. 2001. National Park Service – Rivers and Trails Conservation and Assistance Program, Washington, DC. 27pp.).

The need to clarify a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the segment division to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the bridge”...

Timber management activities on non-federal lands within wild and scenic river corridors are guided by state and local authorities. Under the Wild & Scenic Rivers Act, the only way the federal government can restrict private timber management is through purchase of timber rights (in easement or fee title). The river manager may provide technical assistance and/or work with state/local governments to protect river values.

Generally, no. Any provisions for public use of private lands must be specifically included in the terms of the easement. Depending upon the terms and conditions of each easement, public access rights may or may not be involved. For example, a scenic easement may only involve the protection of narrowly defined visual qualities with no provisions for public use. A trail or road easement by necessity may involve public use provisions.

Yes it may. Once water rights are adjudicated, the federal reserved water right may affect future water development projects, depending upon the impacts of the new proposal on the river’s flow-dependent values. Adjudications have been completed or are in process on 15 designated wild and scenic rivers. To date, existing flows have been sufficient to protect current and future demands and to meet the purposes for which the river was designated. River-administering agencies can work with local and state agencies to negotiate solutions that accommodate future water needs and that protect wild...

These facilities will be provided if they are consistent with the management plan for each river and if funds are available.

A range of projects are allowable to restore natural channel processes and habitat, including placement of limited rock and wood, native plantings to stabilize streambanks, and the removal or addition of fish barriers. Such projects are most likely to protect river values, including a river’s free-flowing condition, provided they: 

  1. Mimic the effects of naturally occurring events such as trees falling in and across the river (including the formation of wood jams), boulders tumbling in or moving down the river course, exposure of bedrock outcrops, bank sloughing or...

Citizen stewards are increasingly important in protecting wild and scenic river values, often through river-specific or regional stewardship organizations. Individually, or through nonprofit entities, citizens help survey and monitor resource conditions, provide interpretive and education opportunities, contribute to restoration efforts, and support many other protection activities.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

For state-designated rivers, a governor may submit an application to the Secretary of the Interior under Section 2(a)(ii) of the Act.  If found eligible, and if sufficient protection is afforded by the state, the Secretary may make the designation.  Rivers designated in this manner continue to be administered by the state (sometimes with assistance from local governments), except for any federal lands along the river.  If there are federal lands located along the river, the state and federal river-administering agencies may enter into an agreement to outline federal/state...

The federal government has rarely exercised its eminent domain powers with respect to wild and scenic rivers. Of the 226 rivers in the National Wild & Scenic Rivers System as of June 2022, condemnation for fee title has been used on only four rivers. Nearly all of the federal government’s use of condemnation occurred in the early years of the Wild & Scenic Rivers Act’s implementation when the attitudinal climate was one of federal acquisition. Similarly, the use of scenic easement condemnation has also been used very rarely, and then only on seven rivers, all designated prior to...

Yes. Section 7(b) of the Wild & Scenic Rivers Act provides the same protection to study rivers authorized by Congress, except that the qualifying word “unreasonably” does not appear before “diminish” for projects located above, below, or on a stream tributary to the study segment’s boundaries. The intent and effect is to provide greater protection for study rivers from proposed hydroelectric facilities or other federally assisted water resource projects during the time-limited study process. Identical protection from water resource projects also applies to rivers that were previously...

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

Section 13(c) of the Wild & Scenic Rivers Act expressly reserves the quantity of water necessary to protect river values, including water quality and flow-dependent outstandingly remarkable values. This reservation of water is called a federal reserved water right and is generally adjudicated in a state court (e.g., basin-wide adjudication). River designation does not supersede existing, valid water rights.

Refer also to CRS Report for Congress, The Wild and Scenic Rivers Act and Federal Water Rights, by Cynthia Brougher (January 9, 2009).

 

...

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under the Wild & Scenic Rivers Act and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.

Prior to completion of the CRMP, proposed projects and new decisions (e.g., issuance of a special-use permit) on federal lands are evaluated by the wild and scenic river-administering agency to ensure they protect and, to the extent possible, enhance river values (free-flowing condition, water quality and outstandingly remarkable values). The necessary evaluation framework is a detailed description of the existing conditions of these values at the time of designation. Absent this information it may not be possible to evaluate the effects of an activity relative to the non-degradation and...

To be eligible for designation, a river must be free-flowing and contain at least one "outstandingly remarkable value," i.e., scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar value.

Section 16(b) of the Wild & Scenic Rivers Act defines a river as “a flowing body of water or estuary, or a section, portion, or tributary thereof, including rivers, streams, creeks, runs, kills, rills, and small lakes.”

(*For some rivers, Congress has directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground circumstances and, therefore, are unlikely to require subsequent amendment.)

Yes. In a very few cases, the legislation designating a river erroneously describes a segment division and needs to be amended to fit on-the-ground circumstances. For example, the designating language for the Upper Rogue Wild & Scenic River...

Ideally one coordinated CRMP is developed with each wild and scenic river-administering agency documenting its respective decisions. In a few cases, separate plans may be required. However, even in this case, the planning process is conducted jointly to the greatest extent possible to ensure consistency of outstandingly remarkable values, classification, standards, and monitoring.

Corridor boundaries are established to protect the free-flowing condition, water quality, and outstandingly remarkable values for which the river was designated. Generally, the corridor width for designated rivers cannot exceed an average of 320 acres per mile which, if applied uniformly along the entire designated segment, is one-quarter of a mile (1,320 feet) on each side of the river. Boundaries may be wider or narrower, but are not to exceed the 320 acre average per mile per Section 3(b) of the Wild & Scenic Rivers Act without approval by Congress. The acreage of any islands...

No. Navigability determinations are based on factors other than wild and scenic river designation. Because of this, designation does not affect ownership of the submerged lands [or minerals lying] under the river.

Generally, existing livestock grazing practices and related structures are not affected by designation. The Interagency Guidelines state that agricultural practices should be similar in nature and intensity to those present in the area at the time of designation, and that grazing may be compatible with all river classifications (wild, scenic or recreational). Grazing and other public uses may occur in a wild and scenic river corridor as long as the uses do not adversely impact or otherwise degrade the values for which a river was designated.

Yes.  There are three classifications (wild, scenic and recreational) that may be applied to a particular river segment. Distinct segments along the designated reach may contain differing and non-overlapping classifications (wild, scenic, or recreational), e.g., a 100-mile wild and scenic river may be classified as wild for 50 miles, scenic for 30 miles, and recreational for 20 miles.

Prior to 1986, Section 3(b) of the Wild & Scenic Rivers Act required the river-administering agency to “prepare a plan for necessary developments in connection with its administration in accordance with such classification.” Through a generic amendment of the Wild & Scenic Rivers Act in 1986, Section 3 was amended with a new subsection requiring a “comprehensive management plan . . . to provide for protection of the river values” (Section 3(d)(1)). The comprehensive river management plan (CRMP) must address:

  1. Resource protection;

  2. Development of lands...

Once rivers have been evaluated and determined eligible for further study, agencies conduct an evaluation to determine if the rivers are “suitable” or “not suitable” for wild and scenic river designation within their resource or land management planning processes (Section 5(d)(1)), or usually as a separate study for congressionally authorized studies (Section 5(a)). In each process, the benefits of protecting river values are weighed against other resource values, issues and alternatives.

Either process is typically accompanied by an environmental document, normally an...

Suitability is an assessment of factors to provide the basis for determining whether to recommend a river for addition to the National Wild & Scenic Rivers System. Suitability is designed to answer these questions:

  1. Should the river’s free-flowing character, water quality, and outstandingly remarkable values (ORVs) be protected, or are one or more other uses important enough to warrant doing otherwise?

  2. Will the river’s free-flowing character, water quality, and ORVs be protected through designation? Is it the best method for protecting the river corridor...

No, not unless necessary to protect public safety, the river’s water quality, or other resource values. Recreational use of our nation’s rivers is increasing in both magnitude and extent, i.e., the types of recreational activities pursued and the technologies being used. Whether and how to restrict recreational use is a key issue in the planning process, which includes extensive local, regional, and national public involvement.

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under various laws and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.

Protective management of federal lands in the river area begins at the time the river segment(s) has been found eligible.  The free-flowing condition, identified outstandingly remarkable values, and classification are protected to the extent authorized under law and subject to valid existing rights.  Affording adequate protection requires sound resource management decisions based on National Environmental Policy Act (NEPA) analysis.  Protective management should be initiated by the administering agency as soon as eligibility is determined.  Specific management...

Yes. Regardless of whether a river is designated as a wild and scenic river, states have special responsibilities and management constraints with respect to state-owned lands underlying navigable waters. These special responsibilities arise from the Public Trust Doctrine, which requires states to exercise regulatory authority over navigable riverbeds to ensure that the paramount right of public use of the rivers and riverbeds for navigation, commerce, recreation, and related purposes is not substantially impaired. As a matter of common law, the states hold lands...

Land acquisition is one tool for protecting and enhancing river values. It may also be an important means of providing public access to a wild and scenic river. Notwithstanding Section 6 of the Wild & Scenic Rivers Act, however, Congress has pre-empted some or all of the Wild & Scenic Rivers Act’s federal land acquisition authorities in the enabling acts for certain wild and scenic rivers where the river study demonstrated that protective zoning or other conservation practices provided adequate safeguards for river values.