The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

The requirements specified for a CRMP in Section 3(d)(1) are most often developed through a separate-in-time planning process. This can result in either an amendment to the direction in the agency’s unit-wide plan o a stand-alone plan, depending on agency practices. For designated rivers that are separate NPS units, the CRMP is the General Management Plan (e.g., St. Croix National Scenic Riverway).

Circumstances where agencies should always seek information and advice from each other are:

  1. In agency inventory and planning processes, and environmental analysis processes for aquatic ecosystems and regional watersheds; and,
  2. When proposed actions have the potential of affecting other agency-administered portions of the river.

Section 16(c) of the Wild & Scenic Rivers Act defines a scenic easement as follows:

“Scenic easement” means the right to control the use of land (including the air space above such land) within the authorized boundaries of a component of the wild and scenic river system, for the purpose of protecting the natural qualities of a designated wild, scenic, or recreational river area, but such control shall not affect, without the owner’s consent, any regular use exercised prior to the acquisition of the easement.

While the Wild & Scenic Rivers...

It depends on whether the collecting activity is commercial or noncommercial in nature and subject to river-administering agency regulation. Mining under the 1872 mining law is a commercial and business activity tied to valid existing rights of claims and is regulated as such (36 CFR 228, 43 CFR 3809, 8365, et al).

Non-commercial mineral collecting for recreational purposes (e.g., hobby collecting, rock-hounding, gold panning, sluicing, or dredging) may be authorized by the Bureau of Land Management or the U.S. Forest Service depending on the amounts collected, size and scale of...

Generally, existing agricultural and grazing practices, and related structures are not affected by designation. The Wild & Scenic Rivers Act does not give federal agencies authority to regulate private land. Consequently, the only effect of designation is to authorize the purchase of easements within the river corridor, and to enable federal agency staff to provide technical assistance to private landowners interested in reducing impacts on the river’s water quality and riparian integrity.

No restrictions to private lands may be applied under the Wild & Scenic Rivers Act. Comprehensive river management plans may establish goals for new construction consistent with classification. There is a wide range of uses compatible with these classifications so long as the overall values and character of the river corridor is maintained. Any effect on private lands would be through state or local zoning. Federal acquisition of lands or development rights would require landowner compensation.

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.

Regardless of the study agency’s eligibility and suitability findings, a Section 5(a) study river is protected by the conditions and restrictions specified in Sections 7(b), 8(b), 9(b), and 12(a) of the Wild & Scenic Rivers Act during the period of the study, plus up to three years after the required report is submitted to Congress. In other words, these protections are independent of the recommendation of the study, allowing for Congressional consideration.

Corridor boundaries are established to protect the free-flowing condition, water quality, and outstandingly remarkable values for which the river was designated. Generally, the corridor width for designated rivers cannot exceed an average of 320 acres per mile which, if applied uniformly along the entire designated segment, is one-quarter of a mile (1,320 feet) on each side of the river. Boundaries may be wider or narrower, but are not to exceed the 320 acre average per mile per Section 3(b) of the Wild & Scenic Rivers Act without approval by Congress. The acreage of any islands...

No. The public’s right to float a particular river does not change with designation. Neither does designation give river users the right to use, occupy, or cross private property without permission.

There are more appropriate and cost-effective ways to ensure resource conservation along wild and scenic rivers than using the Wild & Scenic Rivers Act’s condemnation authority. (Refer to Protecting Resource Values on Non-federal Lands (1996).)

Agencies may acquire properties using appropriated funds under the Land and Water Conservation Fund Act or other authorities. Owners are contacted in order to see if an exchange or voluntary purchase can be negotiated.

No, not unless necessary to protect public safety, the river’s water quality, or other resource values. Recreational use of our nation’s rivers is increasing in both magnitude and extent, i.e., the types of recreational activities pursued and the technologies being used. Whether and how to restrict recreational use is a key issue in the planning process, which includes extensive local, regional, and national public involvement.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

There are no known studies comparing river use levels before and after wild and scenic river designation with changes in use levels of similar non-wild and scenic rivers. Factors other than wild and scenic river designation (i.e., river and water attributes, access to the river, and availability of facilities and commercial services) are considered to be the major influences on river use levels. For wild and scenic rivers, as for other rivers managed by federal agencies, the implementation of permit systems or other limits of use are typically undertaken when use exceeds an acceptable...

There are a number of steps that federal agencies use in their evaluation process:

  • Assessment of free-flowing condition and resource values.
  • Finding of eligibility or ineligibility.
  • Inventoried or tentative classification based on the development of shoreline, watercourse, and access.
  • Establishment of tentative, preliminary, or proposed boundaries and/or river areas.
  • Establishment of protective management requirements for eligible rivers.

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

Landowners can charge a fee for crossing private lands to fish, except where a public access easement exists. The designation of a wild and scenic river does not change landowner rights unless all, or a portion of those use rights, are acquired from the landowner.

Yes.  Congress and the Secretary of the Interior have designated many river segments which are above or below dams that have regulated flows.

Administering agencies do not have any authority to control public use of private lands. Granting of access remains the owner’s responsibility and trespass is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

Yes, per Sections 3(b) and 15(1) for rivers designated by Congress under Section 3(a), but not for rivers designated by the Secretary of the Interior under Section 2(a)(ii). For 2(a)(ii) rivers, states and/or local government set the boundaries, if any, for rivers in their systems; these rivers are not subject to Section 3(b) or the 320/640-acre limitation.

Eligibility findings are made as a part of a congressionally authorized study under Section 5(a), or pursuant to agency inventory and planning under Section 5(d)(1).  For Section 2(a)(ii) rivers, the National Park Service will make an eligibility determination under authority delegated by the Secretary of the Interior following application by the governor(s) for federal designation.

A Section 5(d)(1) study river is protected to the extent of each study agency’s authority and not by the Wild & Scenic Rivers Act. Each agency’s policy is to protect eligible rivers and rivers determined suitable for designation for the life of the respective agency land use plan. A river determined not suitable for designation need no longer be protected as a potential addition to the National Wild & Scenic Rivers System once the study, with its related decision document, is completed.

The Department of Transportation (DOT), in coordination with the river-administering agency, performs compliance reviews for qualifying properties. While Section 4(f) requires that the river-administering agency’s recommendations for minimizing harm are considered during the planning process, the authority to administer and make Section 4(f) approvals ultimately resides with the DOT. The river-administering agency’s concurrence on any DOT Section 4(f) compliance documents should clearly state that its concurrence is contingent upon a favorable final determination for the project under...

Prior to 1986, Section 3(b) of the Wild & Scenic Rivers Act required the river-administering agency to “prepare a plan for necessary developments in connection with its administration in accordance with such classification.” Through a generic amendment of the Wild & Scenic Rivers Act in 1986, Section 3 was amended with a new subsection requiring a “comprehensive management plan . . . to provide for protection of the river values” (Section 3(d)(1)). The comprehensive river management plan (CRMP) must address:

  1. Resource protection;

  2. Development of lands...

Section 8(a) of the Wild & Scenic Rivers Act withdraws public (federal) lands within the authorized boundary of a designated component from entry, sale, or other disposition under the public land laws of the United States.

The need to clarify a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the segment division to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the bridge”...

Through the various federal agencies’ land management planning processes and initiatives by the public, a significant number of rivers have been identified for study as potential additions to the National Wild & Scenic Rivers System. For example, the Nationwide Rivers Inventory (NRI), maintained by the National Park Service, has identified over 3,400 river segments as potential candidates for study and/or inclusion into the National System.

As provided in Sections 4(a) and 5(c) of the Wild & Scenic Rivers Act, the following factors should be considered and, as appropriate, documented as a basis for the suitability determination for each river.

  1. Characteristics which do or do not make the area a worthy addition to the National Wild & Scenic Rivers System. These characteristics are described in the Wild & Scenic Rivers Act (see factors 2 through 7) and may include additional suitability factors (8 through 13).

  2. The current status of land ownership and use in the area.

  3. The...

Rivers included in the National Wild & Scenic Rivers System by act of Congress (under Section 3(a) of the Wild & Scenic Rivers Act) are administered by one of four federal agencies: Bureau of Land Management (BLM), National Park Service (NPS), U.S. Forest Service (USFS), and/or U.S. Fish & Wildlife Service (FWS) as specified in the legislation. Rivers included in the National Wild & Scenic Rivers System at the request of a governor and designated by the Secretary of the Interior (under Section 2(a)(ii) of the Wild & Scenic Rivers Act) are administered by the respective...

Section 16(b) of the Act defines free-flowing as “existing or flowing in a natural condition without impoundment, diversion, straightening, rip-rapping, or other modification of the waterway. The existence, however, of low dams, diversion works and other minor structures at the time any river is proposed for inclusion in the national wild and scenic rivers system shall not automatically bar its consideration for such inclusion: Provided, that this shall not be construed to authorize, intend, or encourage future construction of such structures in components of the national wild and...

Due to the dams, diversions, and water resource development projects that occurred from the 1930’s to the 1960’s, the need for a national system of river protection was recognized by conservationists (notably Frank and John Craighead), congressional representatives (such as Frank Church and John Saylor), and federal agencies.  The Act was an outgrowth of the national conservation agenda of the 1950’s and 1960’s, captured in the 1962 recommendations of the Outdoor Recreation Resources Review Commission.  The Act concluded that selected rivers be preserved in a free-flowing...

Congress may classify the river upon the date of designation or authorize classification by the managing agency.  In the latter case, managing agencies have one year to finalize the boundary, identify the appropriate classification, and publish a notice in the Federal Register.  The agency has three years to complete a management plan.  For Section 2(a)(ii) rivers, classification would be established when the Secretary of the Interior designates the river.

No. Federal agencies do not have the authority to reimburse landowners for damage to their lands as a result of public use. However, wild and scenic river designation is unlikely to increase or invite vandalism. Granting access remains the owner’s responsibility and vandalism is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

Rivers in Alaska outside of national parks and Elkhorn Creek in Oregon (640 acres per river mile) exceed the 320 acre average.

A primary objective of wild and scenic river designation is to protect and enhance riparian area function and other river-related natural values. Specific actions to meet the objective are typically set forth in the management plan required for each river.

Timber management activities on federal lands within wild and scenic river corridors must be designed to help achieve land-management objectives consistent with the protection and enhancement of the values that caused the river to be added to the National Wild & Scenic Rivers System. Management direction needed to protect and enhance the river’s values is developed through the river planning process. Wild and scenic river designation is not likely to significantly affect timber management activities beyond existing measures to protect riparian zones, wetlands, and other resource values...

Examples include, but are not limited to, bank stabilization/revetments; bridges (e.g., abutments, piers, approaches); emergency repairs; channelization; channel restoration; culverts; dams and dam removal; dredging or excavation; fish habitat/passage restoration or enhancement; gravel mining; in-channel transmission towers; levees; pipelines; recreation facilities such as boat ramps and fishing piers; water diversions/wells; and activities that are authorized under Section 404 of the Clean Water Act by the United States Army Corps of Engineers (ACOE).


Review of...

Yes.  The federal agency should consider a wide variety of internal and external sources from which to identify potentially eligible rivers.  These sources may include:  American Rivers’ “Outstanding Rivers List,” statewide river inventories/assessments, published guidebooks, etc.  The important point is to develop and apply standardized criteria through a documented evaluation process for potential wild and scenic rivers.

The federal government has rarely exercised its eminent domain powers with respect to wild and scenic rivers. Of the 226 rivers in the National Wild & Scenic Rivers System as of June 2022, condemnation for fee title has been used on only four rivers. Nearly all of the federal government’s use of condemnation occurred in the early years of the Wild & Scenic Rivers Act’s implementation when the attitudinal climate was one of federal acquisition. Similarly, the use of scenic easement condemnation has also been used very rarely, and then only on seven rivers, all designated prior to...

Generally, no. Restrictions on public boating access and the implementation of entry permit systems (rationing and/or allocation) are not usually related to designation. Limitations on boating usually relate to the amount of use and/or types of user. Those rivers with use levels or types of use beyond acceptable limits (i.e., resulting in impacts to the values) may necessitate restricted access regardless of designation.

No. Lands owned by a state may be acquired only by donation or exchange per Section 6(a)(1) of the Wild & Scenic Rivers Act.

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

A river identified for study under Section 5(d)(1) is protected by each agency’s policy; i.e., the Wild & Scenic Rivers Act provides no statutory protections. To the extent of each agency’s authority, the river’s free-flowing condition, water quality, outstandingly remarkable values, and classification are protected. Prior to a suitability study, the inventoried classification is protected. If, as the result of a suitability study, a less restrictive classification is recommended for a river or portion thereof, the agency is obligated to protect this recommended classification.

Section 13(g) of the Wild & Scenic Rivers Act allows the granting of easements and rights-of-way within the boundaries of designated components in accordance with applicable laws, provided that the conditions attached to the grant are consistent with the purposes of the Wild & Scenic Rivers Act.

Any portion of a right-of-way project that includes federally assisted construction that may affect the river’s free-flowing condition—and is not automatically prohibited by the Wild & Scenic Rivers Act—is subject to an evaluation by the river-administering agency under Section...

River access is evaluated in the land use planning process.  Specific access needs for public enjoyment, as well as any limitations, are determined in the river management plan.  In keeping with the requirements of the Wild & Scenic Rivers Act, “wild” rivers are generally inaccessible, except by trail (no roads); “scenic” rivers are accessible by road, which generally don’t parallel the river; and “recreational” rivers may have parallel or crossing road and railroad access.